Back to projects

Hunter River Treatment Plant upgrade

Hunter River, Prince Edward Island

completeWastewaterMRIF
Federal contribution
$146,878
Federal share33%

of $450.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 5, 2007
20082009
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
May 1, 2008(actual)
Construction end
Feb 24, 2009(actual)

Against the original forecast

  • Construction start20 months lateforecast Sep 1, 2006
  • Construction end14 months lateforecast Dec 31, 2007