Hunter River Treatment Plant upgrade
Hunter River, Prince Edward Island
Federal contribution
$146,878
Federal share33%
of $450.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 5, 2007
20082009
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Community Council of Hunter River
- Construction start
- May 1, 2008(actual)
- Construction end
- Feb 24, 2009(actual)
Against the original forecast
- Construction start20 months lateforecast Sep 1, 2006
- Construction end14 months lateforecast Dec 31, 2007
Also in Hunter River