Wastewater Treatment Facility Improvements

Hunter River, Prince Edward Island

completeWastewaterCC
Federal contribution
$79,792
Federal share33%

of $239.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Construction start
Jun 4, 2009(actual)
Construction end
Aug 2, 2011(actual)

Against the original forecast

  • Construction start11 months earlyforecast May 1, 2010
  • Construction end14 months lateforecast Jun 10, 2010