Seawood Estates Sanitary Sewer Extension
Hunter River, Prince Edward Island
Federal contribution
$365,723
Federal share32%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 6, 2009
200920102011
Built
Approved 5 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Resort Municipality of Hunter River
- Construction start
- May 17, 2009(actual)
- Construction end
- Jul 30, 2011(actual)
Against the original forecast
- Construction start5 months earlyforecast Oct 1, 2009
- Construction end13 months lateforecast Jun 30, 2010
Also in Hunter River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22289 in the federal list. How to read these figures.