Forcemain Replacement-Water Street / Crossroads
Bay Roberts, Newfoundland and Labrador
Federal contribution
$166,077
Federal share33%
of $498.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 27, 2006
200720082009
Built
Approved 6 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Bay Roberts
- Construction start
- Jun 2, 2008(actual)
- Construction end
- Oct 31, 2009(actual)
Against the original forecast
- Construction start21 months lateforecast Sep 1, 2006
- Construction end2.6 years lateforecast Mar 31, 2007