Minitonas Lagoon Expansion

Minitonas-Bowsman, Manitoba

completeWastewaterMRIF
Federal contribution
$277,000
Federal share27%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 9, 2007
2008201020122014
Built

Approved 4 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Minitonas
Construction start
Jul 12, 2012(actual)
Construction end
Nov 18, 2013(actual)

Against the original forecast

  • Construction start5.9 years lateforecast Aug 1, 2006
  • Construction end4 months lateforecast Jul 30, 2013

Also in Minitonas-Bowsman

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15751 in the federal list. How to read these figures.