Minitonas Wastewater and Lagoon Expansion
Federal contribution
$327,670
Federal share33%
of $983.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2014
201520162017
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Minitonas-Bowsman
- Construction start
- Sep 12, 2016(actual)
- Construction end
- Dec 15, 2016(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 29, 2016
- Construction end6 weeks lateforecast Nov 4, 2016
Also in Minitonas-Bowsman
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46021 in the federal list. How to read these figures.