Bridge Repair and Improvement
Federal contribution
$52,200
Federal share33%
of $156.6K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedJan 26, 2010
2010
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Rural Municipality of Minitonas
- Construction start
- Nov 6, 2009(actual)
- Construction end
- Nov 1, 2010(actual)
Against the original forecast
- Construction end4 months lateforecast Jun 30, 2010
Also in Minitonas-Bowsman
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29636 in the federal list. How to read these figures.