Bridge Repair and Improvement

Minitonas-Bowsman, Manitoba

completeHighways and RoadsISF
Federal contribution
$52,200
Federal share33%

of $156.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedJan 26, 2010
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Nov 6, 2009(actual)
Construction end
Nov 1, 2010(actual)

Against the original forecast

  • Construction end4 months lateforecast Jun 30, 2010