Swan Valley Recreation and Wellness Centre
Federal contribution
$400,000
Federal share6%
of $7.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2007
2007200920112013
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Swan River
- Construction start
- Nov 1, 2010(actual)
- Construction end
- Feb 28, 2014(actual)
Against the original forecast
- Construction start4.1 years lateforecast Oct 2, 2006
- Construction end14 months lateforecast Dec 31, 2012
Also in Swan River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15758 in the federal list. How to read these figures.