Swan River - Handi Van Storage Facility
Federal contribution
$52,800
Federal share50%
of $105.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2018
Built
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Town of Swan River
- Construction start
- Jun 5, 2017(actual)
- Construction end
- Dec 29, 2017(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Aug 1, 2017
- Construction end3 months earlyforecast Mar 31, 2018