6th Avenue Wastewater Pump Station Upgrade

Swan River, Manitoba

completeWastewaterCWWF
Federal contribution
$500,000
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 18, 2017
2018
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Swan River
Construction start
Jul 26, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 26, 2017
  • Construction end4 weeks lateforecast May 31, 2018