Back to projects

Water filtration plant brought up to standards

Saint-Zénon, Quebec

completeDrinking WaterMRIF
Federal contribution
$100,000
Federal share25%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 4, 2007
2007200820092010
Built

Approved 9 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Apr 1, 2009(actual)
Construction end
Mar 31, 2010(actual)

Also in Saint-Zénon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15800 in the federal list. How to read these figures.