Asphalt repairs on Highway 131 in the Municipality of Saint-Zénon
Federal contribution
$850,000
Federal share50%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 2, 2010(actual)
- Construction end
- Sep 22, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 15, 2010
- Construction end6 weeks earlyforecast Oct 31, 2010
Also in Saint-Zénon