Trail #40 and link between trails 40 and 45, St Zénon sector

Saint-Zénon, Quebec

completeRecreationNRT
Federal contribution
$32,000
Federal share50%

of $64.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
2016
Built

Approved 13 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
Club Quad St-Zénon
Construction start
May 20, 2015(actual)
Construction end
Dec 21, 2015(actual)