New multifunctional community centre
Federal contribution
$706,306
Federal share33%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 14, 2009
20092010
Built
Approved 20 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Société Sportive Et Sociale De Saint-Sylvestre
- Construction start
- Jun 26, 2009(actual)
- Construction end
- Nov 27, 2009(actual)
Against the original forecast
- Construction start11 months lateforecast Aug 7, 2008
- Construction end3 months earlyforecast Feb 28, 2010
Also in Saint-Sylvestre
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15852 in the federal list. How to read these figures.