Water Systems Upgrades
Federal contribution
$121,697
Federal share40%
of $304.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Sylvestre
- Construction start
- May 31, 2021(actual)
- Construction end
- Mar 15, 2022(actual)
Against the original forecast
- Construction end9 months earlyforecast Dec 15, 2022