Water Systems Upgrades

Saint-Sylvestre, Quebec

completeWastewaterGIS
Federal contribution
$121,697
Federal share40%

of $304.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Sylvestre
Construction start
May 31, 2021(actual)
Construction end
Mar 15, 2022(actual)

Against the original forecast

  • Construction end9 months earlyforecast Dec 15, 2022