Installation of water games
Federal contribution
$60,861
Federal share33%
of $182.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 23, 2021
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Saint-Sylvestre
- Construction start
- Aug 5, 2021(actual)
- Construction end
- Sep 10, 2021(actual)
Also in Saint-Sylvestre
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57742 in the federal list. How to read these figures.