South West Sanitary Collection System

Turner Valley, Alberta

completeWastewaterMRIF
Federal contribution
$676,037
Federal share33%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 24, 2007
20072008200920102011
Built

Approved 5 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Turner Valley
Construction start
Jul 23, 2007(actual)
Construction end
Sep 22, 2011(actual)

Against the original forecast

  • Construction start7 months lateforecast Jan 1, 2007
  • Construction end18 months lateforecast Mar 31, 2010

Also in Turner Valley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16155 in the federal list. How to read these figures.