South West Sanitary Collection System
Federal contribution
$676,037
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 24, 2007
20072008200920102011
Built
Approved 5 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Turner Valley
- Construction start
- Jul 23, 2007(actual)
- Construction end
- Sep 22, 2011(actual)
Against the original forecast
- Construction start7 months lateforecast Jan 1, 2007
- Construction end18 months lateforecast Mar 31, 2010
Also in Turner Valley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16155 in the federal list. How to read these figures.