North Lift Station
Federal contribution
$199,769
Federal share33%
of $599.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20152016
Built
Approved 23 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Turner Valley
- Construction start
- May 1, 2015(actual)
- Construction end
- Nov 30, 2015(actual)
Against the original forecast
- Construction start10 months lateforecast Jul 1, 2014
- Construction end4 weeks lateforecast Oct 31, 2015
Also in Turner Valley