North Lift Station

Turner Valley, Alberta

completeWastewaterCC
Federal contribution
$199,769
Federal share33%

of $599.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20152016
Built

Approved 23 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Turner Valley
Construction start
May 1, 2015(actual)
Construction end
Nov 30, 2015(actual)

Against the original forecast

  • Construction start10 months lateforecast Jul 1, 2014
  • Construction end4 weeks lateforecast Oct 31, 2015

Also in Turner Valley