Sheep River Inter-Municipal Library
Federal contribution
$888,060
Federal share30%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Turner Valley
- Construction start
- May 7, 2010(actual)
- Construction end
- Aug 30, 2011(actual)
Against the original forecast
- Construction start6 months lateforecast Nov 1, 2009
- Construction end2 months earlyforecast Oct 31, 2011
Also in Turner Valley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28865 in the federal list. How to read these figures.