Back to projects

Sheep River Inter-Municipal Library

Turner Valley, Alberta

completeCultureISF
Federal contribution
$888,060
Federal share30%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Turner Valley
Construction start
May 7, 2010(actual)
Construction end
Aug 30, 2011(actual)

Against the original forecast

  • Construction start6 months lateforecast Nov 1, 2009
  • Construction end2 months earlyforecast Oct 31, 2011

Also in Turner Valley