Chopper Pump Enhancement Technology for Wastewater Treatment
Fort Simpson, Northwest Territories
Federal contribution
$14,190
Federal share26%
of $55.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20072009201120132015
Built
Approved 9.3 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Fort Simpson
- Construction start
- Nov 23, 2006(actual)
- Construction end
- Mar 21, 2012(actual)
Against the original forecast
- Construction start3 weeks lateforecast Nov 1, 2006
- Construction end5.1 years lateforecast Jan 31, 2007
Also in Fort Simpson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16414 in the federal list. How to read these figures.