Booster Station Upgrade and Water Main Extension

Meadow Lake, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$104,500
Federal share25%

of $418.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 5, 2007
20072008
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Meadow Lake
Construction start
Dec 20, 2006(actual)
Construction end
Apr 15, 2008(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 1, 2007
  • Construction end11 months earlyforecast Mar 31, 2009

Also in Meadow Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16426 in the federal list. How to read these figures.