Back to projects

Replacement of Bridge 25

Wellington North, Ontario

completeHighways and RoadsMRIF
Federal contribution
$129,333
Federal share33%

of $388.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
200720082009
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Dec 22, 2006(actual)
Construction end
Apr 17, 2009(actual)

Against the original forecast

  • Construction start6 months lateforecast Jul 2, 2006
  • Construction end13 months lateforecast Mar 31, 2008

Also in Wellington North