Cork Street Sewage Pumping Station

Wellington North, Ontario

completeWastewaterISF
Federal contribution
$600,000
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Apr 1, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Mar 5, 2010