Federal contribution
$496,326
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2015
2016
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Township of Wellington North
- Construction start
- May 16, 2016(actual)
- Construction end
- Nov 11, 2016(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2016
- Construction end14 months earlyforecast Dec 31, 2017