Back to projects

Cst. Rick Hopkins Bridge Rehabilitation

Wellington North, Ontario

completeHighways and RoadsSCF
Federal contribution
$496,326
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2015
2016
Built

Approved 3 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 16, 2016(actual)
Construction end
Nov 11, 2016(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2016
  • Construction end14 months earlyforecast Dec 31, 2017

Also in Wellington North