Grid Road Reconstruction
Foam Lake No. 276, Saskatchewan
Federal contribution
$90,397
Federal share25%
of $361.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 5, 2007
20072008
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Foam Lake
- Construction start
- Dec 20, 2006(actual)
- Construction end
- Dec 19, 2007(actual)
Against the original forecast
- Construction start3 months earlyforecast Apr 1, 2007
- Construction end3 months earlyforecast Mar 31, 2008
Also in Foam Lake No. 276
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16486 in the federal list. How to read these figures.