RM of Foam Lake No. 276 - Landfill Decommissioning

Foam Lake No. 276, Saskatchewan

completeSolid Waste ManagementGIS
Federal contribution
$74,437
Federal share40%

of $186.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2022
20232024
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 25, 2023(actual)
Construction end
Feb 29, 2024(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2023
  • Construction end4 weeks earlyforecast Mar 31, 2024