Sewage Lagoon

Foam Lake No. 276, Saskatchewan

completeWastewaterSCF
Federal contribution
$408,076
Federal share28%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 5, 2019
2020
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 11, 2020(actual)
Construction end
Aug 11, 2020(actual)

Against the original forecast

  • Construction start10 months lateforecast Jul 15, 2019
  • Construction end8 months earlyforecast Mar 31, 2021

Also in Foam Lake No. 276

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53052 in the federal list. How to read these figures.