Replacement of Hughes Creek Bridge
Federal contribution
$163,883
Federal share33%
of $491.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2007
20072008
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of East Hawkesbury
- Construction start
- Feb 1, 2007(actual)
- Construction end
- Jul 7, 2008(actual)
Against the original forecast
- Construction start5 months earlyforecast Jul 15, 2007
- Construction end9 months lateforecast Oct 15, 2007