Energy Upgrades at Centre d'Action
Federal contribution
$75,456
Federal share80%
of $94.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Corporation of the Township of East Hawkesbury
- Construction start
- Jun 12, 2022(actual)
- Construction end
- Mar 31, 2023(actual)
Against the original forecast
- Construction start15 months lateforecast Mar 18, 2021
- Construction end3 months lateforecast Dec 31, 2022
Also in East Hawkesbury