Storm Sewer Replacement - Village of St-Eugene
Federal contribution
$516,511
Federal share40%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 28, 2021
2021202220232024
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Corporation of the Township of East Hawkesbury
- Construction start
- Jul 18, 2022(actual)
- Construction end
- Dec 31, 2023(actual)
Also in East Hawkesbury
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57394 in the federal list. How to read these figures.