Water Supply Line/Filtered Water Service

Preeceville, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$114,496
Federal share25%

of $458.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2008
2009
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Preeceville
Construction start
May 7, 2008(actual)
Construction end
Aug 31, 2009(actual)

Against the original forecast

  • Construction end7 months earlyforecast Mar 31, 2010

Also in Preeceville