Rural Municipality of Preeceville No. 334 - Ebel Bridge
Federal contribution
$166,700
Federal share17%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 18, 2023
202320242025
Built
Approved 5 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Preeceville No. 334
- Construction start
- May 28, 2025(actual)
- Construction end
- Aug 5, 2025(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jul 1, 2025
- Construction end5 months earlyforecast Dec 31, 2025
Also in Preeceville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64057 in the federal list. How to read these figures.