Grid Road Reconstruction
Federal contribution
$49,524
Federal share25%
of $198.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 14, 2007
20082009
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Preeceville
- Construction start
- Jul 24, 2007(actual)
- Construction end
- Dec 16, 2008(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2007
- Construction end9 months lateforecast Mar 31, 2008
Also in Preeceville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16813 in the federal list. How to read these figures.