Back to projects

Installation of Recycling Containers

Elliot Lake, Ontario

completeSolid Waste ManagementMRIF
Federal contribution
$8,298
Federal share33%

of $24.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
20072008
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Elliot Lake
Construction start
Apr 1, 2007(actual)
Construction end
Dec 31, 2007(actual)

Against the original forecast

  • Construction end2.7 years earlyforecast Sep 30, 2010

Also in Elliot Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16593 in the federal list. How to read these figures.