Pearson Drive Watermain

Elliot Lake, Ontario

completeDrinking WaterISF
Federal contribution
$263,286
Federal share28%

of $931.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Elliot Lake
Construction start
Nov 6, 2009(actual)
Construction end
Jun 11, 2010(actual)

Against the original forecast

  • Construction end4 months earlyforecast Sep 30, 2010

Also in Elliot Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31433 in the federal list. How to read these figures.