Transit Expansion and Improvements
Federal contribution
$375,000
Federal share40%
of $937.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 18, 2020
today
2021202320252027
BuiltForecast
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Elliot Lake
- Construction start
- Jun 1, 2022(forecast)
- Construction end
- Jun 30, 2027(forecast)