Repair of waste water pumping systems that services approximately 6000 homes due to failure at 2 Scott Road, Elliot Lake, Ontario.

Elliot Lake, Ontario

completeWastewaterCWWF
Federal contribution
$198,743
Federal share50%

of $397.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Elliot Lake
Construction start
Jun 1, 2019(actual)
Construction end
Aug 29, 2019(actual)

Against the original forecast

  • Construction start13 months lateforecast May 1, 2018
  • Construction end4 months earlyforecast Dec 31, 2019

Also in Elliot Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50114 in the federal list. How to read these figures.