Repair of waste water pumping systems that services approximately 6000 homes due to failure at 2 Scott Road, Elliot Lake, Ontario.
Federal contribution
$198,743
Federal share50%
of $397.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Elliot Lake
- Construction start
- Jun 1, 2019(actual)
- Construction end
- Aug 29, 2019(actual)
Against the original forecast
- Construction start13 months lateforecast May 1, 2018
- Construction end4 months earlyforecast Dec 31, 2019
Also in Elliot Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50114 in the federal list. How to read these figures.