Replacement of a Bridge on Dayton Road in Day Township
Federal contribution
$42,000
Federal share33%
of $126.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2007
20072008
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Huron Shores
- Construction start
- Aug 31, 2007(actual)
- Construction end
- Oct 17, 2008(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2007
- Construction end2 months earlyforecast Dec 30, 2008
Also in Huron Shores
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16701 in the federal list. How to read these figures.