Replacement of a Bridge on Dayton Road in Day Township

Huron Shores, Ontario

completeHighways and RoadsMRIF
Federal contribution
$42,000
Federal share33%

of $126.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
20072008
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Aug 31, 2007(actual)
Construction end
Oct 17, 2008(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2007
  • Construction end2 months earlyforecast Dec 30, 2008