Back to projects

Dayton Road Loop (sections 9-11)

Huron Shores, Ontario

completeHighways and RoadsISF
Federal contribution
$133,333
Federal share33%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 1, 2009(actual)
Construction end
Nov 30, 2009(actual)

Against the original forecast

  • Construction start2 months earlyforecast Dec 1, 2009
  • Construction end6 months earlyforecast May 31, 2010

Also in Huron Shores