Rehabilitation of Maple Ridge Road

Huron Shores, Ontario

completeHighways and RoadsISF
Federal contribution
$24,898
Federal share29%

of $86.0K total eligible cost; the rest comes from other partners.

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 29, 2009(actual)
Construction end
Aug 17, 2009(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 19, 2009
  • Construction end2 weeks earlyforecast Aug 31, 2009

Also in Huron Shores

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32502 in the federal list. How to read these figures.