Shubenacadie Water System Upgrade - Phase 1
Federal contribution
$704,525
Federal share33%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2007
2007200820092010
Built
Approved 5 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of the District of East Hants
- Construction start
- Jan 28, 2008(actual)
- Construction end
- Aug 31, 2010(actual)
Against the original forecast
- Construction start2.2 years lateforecast Nov 24, 2005
- Construction end5 months lateforecast Mar 31, 2010
Also in Shubenacadie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16894 in the federal list. How to read these figures.