Milford Sewage Collection System Upgrades
Federal contribution
$179,794
Federal share33%
of $539.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20122013201420152016
Built
Approved 4.6 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of the District of East Hants
- Construction start
- Nov 1, 2012(actual)
- Construction end
- Jul 16, 2015(actual)
Against the original forecast
- Construction start18 months earlyforecast May 15, 2014
- Construction end6 weeks earlyforecast Aug 30, 2015
Also in Shubenacadie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27187 in the federal list. How to read these figures.