Back to projects

Engineered Spring-Grand Lake to Shubenacadie River

Shubenacadie, Nova Scotia

completeDrinking WaterCC Top Up
Federal contribution
$616,204
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Nov 16, 2009(actual)
Construction end
Jul 31, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 22, 2009

Also in Shubenacadie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26867 in the federal list. How to read these figures.