Water Treatment Plant Upgrades

Swift Current, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$990,847
Federal share13%

of $7.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 6, 2007
200720082009201020112012
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Swift Current
Construction start
Dec 20, 2006(actual)
Construction end
Nov 15, 2011(actual)

Against the original forecast

  • Construction end5 months earlyforecast Mar 31, 2012

Also in Swift Current

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16966 in the federal list. How to read these figures.