Pathway Connectivity for Swift Current, Saskatchewan

Swift Current, Saskatchewan

completeActive TransportationATF
Federal contribution
$329,319
Federal share60%

of $548.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 15, 2023
20232024
Built

Approved 12 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Swift Current
Construction start
Aug 9, 2024(actual)
Construction end
Nov 4, 2024(actual)

Against the original forecast

  • Construction start14 months lateforecast Jun 5, 2023
  • Construction end12 months lateforecast Oct 27, 2023

Also in Swift Current

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64242 in the federal list. How to read these figures.