Water Treatment

Swift Current, Saskatchewan

completeDrinking WaterCC
Federal contribution
$216,666
Federal share33%

of $650.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010201120122013
Built
Program
Building Canada Fund - Communities Component
Construction start
Nov 24, 2009(actual)
Construction end
Dec 5, 2012(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 22, 2009
  • Construction end16 months earlyforecast Mar 31, 2014

Also in Swift Current

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26921 in the federal list. How to read these figures.