Cape Dorset Retrofit to Arena
Federal contribution
$142,034
Federal share50%
of $284.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20082010201220142016
Built
Approved 8.8 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Government of Nunavut
- Construction start
- May 25, 2007(actual)
- Construction end
- Oct 1, 2008(actual)
Against the original forecast
- Construction start8 weeks lateforecast Apr 1, 2007
- Construction end6 months earlyforecast Mar 31, 2009
Also in Iqaluit