Back to projects

Sewage Treatment Plant Upgrade

Wabush, Newfoundland and Labrador

completeWastewaterMRIF
Federal contribution
$376,402
Federal share32%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 25, 2008
2008200920102011
Built

Approved 10 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Wabush
Construction start
Aug 20, 2007(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2007