Industrial Park Wastewater Treatment Plant

Wabush, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$5.1M
$5,078,275
Federal share40%

of $12.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 15, 2019
2020202120222023
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Wabush
Construction start
Aug 1, 2020(actual)
Construction end
Jan 18, 2023(actual)

Against the original forecast

  • Construction start4 months earlyforecast Dec 15, 2020
  • Construction end11 months earlyforecast Dec 18, 2023