Arena Renovations
Wabush, Newfoundland and Labrador
Federal contribution
$475,308
Federal share20%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Wabush
- Construction start
- Feb 7, 2012(actual)
- Construction end
- Mar 31, 2013(actual)
Against the original forecast
- Construction start7 months earlyforecast Sep 1, 2012
Also in Wabush
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26685 in the federal list. How to read these figures.